National Highways construction to decline by 7-10% in FY25, amid execution challenges: CareEdge Ratings

0
12

New Delhi,feb 7
The pace of National highway construction in India is expected to decline by approximately 7-10 per cent in FY25, with construction slowing from 12,350 km in FY24 to an estimated 11,100-11,500 km in FY25, translating to a rate of nearly 31 kilometre per day, according to CareEdge Ratings.The slowdown is attributed to execution challenges, intensifying competition, and significant delays in the receipt of appointed dates after project awards.
Maulesh Desai, Director, CareEdge Ratings, said, “Among the under-construction projects, totalling Rs 1.83 lakh crore, 55 per cent with an aggregate BPC of Rs 1 lakh crore are delayed by more than six months.”He added, “It is owing to escalating execution challenges, heightened competitive landscape, and significant delay in receipt of appointed dates post award of the project.”CareEdge Ratings conducted an extensive financial analysis of 17 sponsors and EPC contractors engaged in Hybrid Annuity Model (HAM) projects.While timely execution contributed to a 14 per cent compound annual growth rate (CAGR) in total operating income (TOI) between FY21 and FY24, lower project awards in FY24 and H1FY25 have significantly reduced revenue visibility.The order book-to-TOI ratio declined from 2.78x in FY22 to 2.15x in FY24, with many projects awaiting appointed dates, leading to a much lower executable order book.
Furthermore, operating profitability is projected to decline by 200 basis points (bps) in FY25 from FY23 levels due to higher competition and increased overhead costs. The discontinuation of the Atma Nirbhar Bharat scheme for monthly payments is expected to lengthen the working capital cycle by 15-20 days in FY25, further straining developers.The Hybrid Annuity Model (HAM) continues to dominate highway project awards, accounting for nearly 55 per cent of total projects awarded between FY21 and FY24.
CareEdge Ratings analysed 374 HAM projects awarded by the National Highways Authority of India (NHAI) between 2015 and 2024, covering 16,000 km with a total BPC exceeding Rs 4.03 lakh crore. New Delhi [India], February 7 (ANI): India has achieved a historic milestone by surpassing 100 GW of installed solar power capacity, reinforcing its position as a global leader in renewable energy.This remarkable achievement is a testament to the nation’s commitment to a cleaner, greener future and marks a significant step toward realizing its ambitious target of 500 GW of non-fossil fuel-based energy capacity by 2030 set by Prime Minister Narendra Modi, a Ministry of New and Renewable Energy release said.Union Minister of New and Renewable Energy Pralhad Joshi said India is becoming self-reliant in green energy.