Jammu, July 24:
Superintending Engineer EM & RE Circle Kathua has informed that, to execute work of testing of CT/PT units by M/S ERDA, the shutdown of 11 KV feeders is being observed. During the shutdown, the power supply to All Industrial Units Industry-III IGC Phase-I Samba will remain affected on July 25, 27 and 30 from 10 am to 3 pm. Similarly, the power supply to All Industrial Units Industry-II IGC Phase-I Samba will remain affected on July 26, 29 and 31 from 10 am to 3 pm.